Master interconnect module with 10G interconnect link module cabling example

Prerequisites
HPE Synergy master and satellite interconnect module cabling (nonredundant)
Item Description Amount
1 HPE Virtual Connect SE 40Gb F8 Module for HPE Synergy

(primary master ICM)

1
2 HPE Virtual Connect SE 40Gb F8 Module for HPE Synergy

(secondary master ICM)

1
3 HPE Synergy 10Gb Interconnect Link Modules

(satellite ICM)

8

Procedure

  1. Using interconnect link cables, connect the primary master switch ports to each satellite ICM in the same bay.

    Connect the L1, L2, L3, or L4 ports on the master ICM to the L1 port on each satellite ICM.

    Figure 104: Primary master ICM cabled to satellite ICMs

  2. Using interconnect link cables, connect the secondary master switch ports to each satellite ICM in the same bay.

    Connect the L1, L2, L3, or L4 ports on the master ICM to the L1 port on each satellite ICM.

    Figure 105: Secondary master ICM cabled to satellite ICMs

  3. Cable two stacking cables from the primary master ICM to the secondary master ICM.
    1. Connect a stacking cable from port Q7 on the first master to port Q7 on the second module.
    2. Connect a stacking cable from port Q8 on the first master to port Q8 on the second module.
    Figure 106: Multiframe stacking example

  4. Cabling is complete.

    Figure 107: Complete cabling for master and satellite interconnect modules in multiple frames (redundant)Five-frame configuration with Image Streamer