Shutting down RHOCP

Procedure
  1. Back up switch configuration data.
  2. Back up etcd data.
  3. Back up projects and PVC yaml files of HPE Nimble storage.
  4. Check certificates expiry date of a cluster.
  5. Regenerate certificates, if required or skip this step.
  6. Create temporary service admin for cluster.
  7. Shut down the worker nodes, then shutdown the master node.